Dubai renovation guide
Kitchen & Bathroom Renovation Costs in Dubai
Kitchens and bathrooms are the most expensive rooms in any Dubai renovation because they concentrate plumbing, electrical, waterproofing, tiling and joinery into small spaces. A kitchen runs from AED 15,000 for a basic refit to well over AED 100,000 for a luxury build; a bathroom runs from AED 8,000 to AED 50,000 or more per room.
This guide itemises where the money goes in each room, explains the quality checks that matter for wet work, particularly waterproofing, and sets out realistic timelines so you can hold a contractor to a sensible programme.
Kitchen renovation cost breakdown
A basic kitchen refit in Dubai costs AED 15,000 to 30,000: laminate or melamine cabinetry, a quartz or granite counter, standard tiles and reconnection of existing appliances. A mid-range kitchen at AED 30,000 to 70,000 buys spray-painted MDF or acrylic cabinetry, better hardware, a full-height splashback and new mid-tier appliances.
Luxury kitchens start around AED 100,000, driven by imported cabinetry systems, natural stone or sintered surfaces, integrated appliances and often layout changes that relocate plumbing and gas. Cabinetry is consistently the largest line at 35 to 45 percent of the total, followed by counters, appliances and labour.
| Component | Basic | Mid-range | Luxury |
|---|---|---|---|
| Cabinetry | AED 6,000 - 12,000 | AED 12,000 - 30,000 | AED 45,000+ |
| Counters and splashback | AED 3,000 - 6,000 | AED 6,000 - 15,000 | AED 20,000+ |
| Appliances | AED 3,000 - 6,000 | AED 8,000 - 15,000 | AED 30,000+ |
| Labour and MEP | AED 3,000 - 6,000 | AED 6,000 - 12,000 | AED 15,000+ |
Bathroom renovation cost breakdown
A basic bathroom refit costs AED 8,000 to 20,000 per room: local ceramic tiles, standard sanitaryware, a framed shower screen and new waterproofing. Mid-range bathrooms at AED 20,000 to 50,000 add porcelain or large-format tiles, branded fittings, a concealed cistern and better vanity joinery.
Luxury bathrooms start at AED 50,000 and rise with natural stone, frameless glass, rain showers, underfloor considerations and custom vanities. Roughly a third of any bathroom budget is invisible when finished, demolition, plumbing, waterproofing and screed, which is exactly the third you should never economise on.
Two cost drivers deserve attention when comparing quotes. Relocating the toilet or shower drain means breaking into the floor slab and rerouting drainage, which can add AED 3,000 to 8,000 per bathroom, so keeping fixtures in their existing positions is the single biggest saving available. Glass is the other: a frameless shower enclosure costs two to three times a framed one, and it is frequently listed as an exclusion in the quote.
Where to spend and where to save
In kitchens, spend on the carcass hardware and the counter, hinges, runners and stone are used daily for years and are painful to replace, and save on door finishes and handles, which are cosmetic and easy to swap later. Mid-tier appliances from established brands perform close to premium ones at a fraction of the price.
In bathrooms, spend on waterproofing, plumbing quality and the shower mixer, the items buried in the wall, and save on accessories, mirrors and cabinet finishes. A basic tile laid perfectly reads better than an expensive tile laid badly, so the tiler's skill matters more than the tile budget in most rooms.
Wet-work quality checks
Waterproofing is the single most important item in a bathroom renovation. The standard practice in Dubai is a liquid-applied membrane over the floor and up the walls in wet zones, followed by a 24-hour flood test: the floor is flooded, the drain plugged, and the level checked the next day with the ceiling below inspected for leaks. Insist that this test happens and ask for photographs before tiling proceeds.
Beyond waterproofing, check that floor falls direct water to the drain without pooling, that pressure testing is done on new plumbing lines, and that tile lippage and grout lines are consistent. Kitchens need their own checks: isolation valves on supply lines, proper trap connections and, where gas is present, work by a licensed gas contractor.
Get waterproofing and pressure-test records in writing. If a leak appears a year later, those records are the difference between a warranty claim and an argument, and building management will ask for them if the unit below is affected.
- Liquid membrane applied to floor and wet-zone walls
- 24-hour flood test completed and photographed before tiling
- Floor falls tested, no pooling away from the drain
- Pressure test on new water supply lines
- Isolation valves fitted and accessible
Timeline expectations
A kitchen renovation takes two to four weeks on site once materials are in hand: demolition and MEP first, then cabinetry installation, counter templating and fitting, and finally appliances and snagging. The counter is the usual bottleneck, quartz and stone are templated after cabinets are in and take five to ten days to fabricate.
A bathroom takes one to three weeks per room: demolition, plumbing and waterproofing in week one, tiling in week two, and fittings, glass and snagging in week three. Add lead time before site work starts, imported cabinetry and sanitaryware can take four to eight weeks to arrive, so confirm material availability before demolition begins, not after.
If you are renovating multiple bathrooms while living in the unit, sequence them one at a time so a working bathroom is always available. Doing kitchen and bathrooms together in an unoccupied unit is more efficient: the same plumbing and tiling teams move between rooms and the overall programme compresses to four to six weeks.
Mistakes to avoid
The most expensive mistakes in kitchen and bathroom projects are sequencing errors: demolishing before materials are confirmed, tiling before the flood test, or ordering counters before cabinets are installed. Each one either stretches the programme or forces rework.
The second category is scope gaps. Quotes that exclude appliances, glass shower screens, accessories or waste removal look cheaper until the extras arrive as variations. The third is skipping approvals: bathroom and kitchen work that relocates plumbing usually needs building NOC and sometimes DM approval, and unapproved work can void insurance and complicate resale.
Finally, avoid selecting a contractor on price alone for wet work. Comparing at least three licensed contractors on itemised scope, waterproofing method and warranty terms, rather than the bottom-line figure, is the cheapest insurance available for the rooms most likely to leak.
Frequently asked questions
How much does a kitchen renovation cost in Dubai?
A basic refit costs AED 15,000 to 30,000, a mid-range kitchen AED 30,000 to 70,000, and a luxury kitchen with imported cabinetry starts around AED 100,000. Cabinetry is usually the largest single cost at 35 to 45 percent of the total.
How much does a bathroom renovation cost in Dubai?
Expect AED 8,000 to 20,000 per bathroom for a basic refit, AED 20,000 to 50,000 for mid-range, and AED 50,000 or more for luxury finishes. Around a third of the budget goes on demolition, plumbing and waterproofing that you never see once tiled.
What is a 24-hour flood test?
After waterproofing, the bathroom floor is flooded with water, the drain is plugged, and the level is checked 24 hours later while the ceiling below is inspected. It is the standard verification in Dubai that a membrane is watertight, and it must happen before tiling starts.
How long do kitchen and bathroom renovations take?
A kitchen takes two to four weeks on site and a bathroom one to three weeks per room, once materials are available. Imported cabinetry and sanitaryware can add four to eight weeks of lead time, so confirm delivery dates before demolition.
Do I need a permit to renovate a kitchen or bathroom in Dubai?
You always need your building management NOC. If the work relocates plumbing, drainage or electrical circuits, a Dubai Municipality permit is usually required as well, and only a licensed contractor can apply for it.